The Alkimos Project - Public Environmental Review

Environmental Information for Wastewater Treatment Plant

The Project was proposed to be developed on one of two possible sites:

  • Site B – the site identified in the current Metropolitan Region Scheme (MRS), and as agreed with Landcorp; or
  • Site A – the alternative site (Lot 101) purchased for this purpose in 1987 and as zoned for this use in the previous MRS.

The Water Corporation is constructing the Alkimos Wastewater Treatment Plant (WWTP) at Site B, with an ocean outlet.  Site B was chosen as the agreed site for the WWTP so that the land most desirable for urban development, to the west, could be available for residential development and the development of the beach as a regional focal point.  

Public Environmental Review

The proposed WWTP and ocean outlet at Alkimos will be constructed in the Coastal Ward of the City of Wanneroo.  Alkimos is located approximately 40km north-west of the Perth CBD in the north-west corridor, between Quinns Rock and Yanchep.

Treated wastewater will be disposed of through an ocean outlet, extending approximately 3.5km offshore from the coast adjacent to the WWTP.  The proposal involves the construction, operation and maintenance of a WWTP at Alkimos, to be developed in stages up to an operational capacity of 160 ML/day beyond 2050.

The Water Corporation proposed two sites for its WWTP.  Site A was located between 300 to 1,000 metres from the Alkimos shoreline behind the foredunes. Site B was located between 1,000 and 1,700 metres from the coast at a higher point in the landscape.

The Environmental Protection Authority has assessed these two options: 1) Site A under assessment number 1582 and 2) Site B under assessment number 1529.

In accordance with the Environmental Protection Act, the Water Corporation prepared a Public Environmental Review (PER) that describes this proposal and its likely effects on the environment.

Alkimos Performance and Compliance Report 2008-2009

The Alkimos Performance and Compliance Report 2008-2009 has been prepared by the Alkimos Water Alliance for construction works associated with the Alkimos Wastewater Scheme. It documents the Alliance's performance over the past year and compliance with Ministerial Statement 755 through the management of environmental aspects associated with the construction of the Scheme.

The Report, which assesses or measures all alliance management plans and procedures, has been prepared to satisfy Condition 4 of Ministerial Statement 755 (November, 2007).

The previous Alkimos Performance and Compliance Report 2007-2008 is also available.

 Alkimos Performance and Compliance Report 2008-2009
  
 Alkimos Performance and Compliance Report 2007-2008
  

For further information on the report and related appendices please contact Environmental Coordinator, Virginia Piscioneri on 9420 3345 or email virginia.piscioneri@watercorporation.com.au or Alliance Relationship Manager, Daniel Rossi on 9420 3824 or email daniel.rossi@watercorporation.com.au.

Alkimos Wastewater Treatment Plant Marine Treated Wastewater Discharge Monitoring and Management Plan

The Monitoring and Management Plan for marine treated wastewater discharge from the Alkimos Wastewater Treatment Plant aims to ensure that it is managed to achieve the following Environmental Quality Objectives. These are described in the document, Perth's Coastal Waters; Environmental Values and Objectives (Environmental Protection Authority, February 2000).

• Environmental Quality Objective 1 (Maintenance of ecosystem integrity), with spatially-assigned levels of protection as shown in figure 2 of schedule 1 of Ministerial Statement 755  (November, 2007);
• Environmental Quality Objective 2 (Maintenance of aquatic life for human consumption) assigned to all parts of the marine environment surrounding the Alkimos ocean outlet with the exception of zones shown in figure 2 of schedule 1 of Ministerial Statement 755  (November, 2007); and
• Environmental Quality Objectives 3 and 4 (Maintenance of primary contact recreation values, and Maintenance of secondary contact recreation values) assigned to all parts of the marine environment surrounding the Alkimos ocean outlet with the exception of zones shown in figure 2 of schedule 1 of Ministerial Statement 755  (November, 2007).

The Monitoring and Management Plan for marine treated wastewater discharge from the Alkimos Wastewater Treatment Plant has been prepared to satisfy Condition 11-1 as specified in Ministerial Statement 755 (November, 2007).

 Alkimos Marine Monitoring and Management Plan
  
 Alkimos Marine Monitoring and Management Plan - Appendix 1
  
 Alkimos Marine Monitoring and Management Plan - Appendix 2
  
 Alkimos Marine Monitoring and Management Plan - Appendix 3
  
 Alkimos Marine Monitoring and Management Plan - Appendix 4
  

Alkimos Wastewater Treatment Plant Odour Management Plan

The Odour Management Plan for the Alkimos Wastewater Treatment Plant aims to ensure that the plant is designed, constructed and operated to manage the potential impacts of odour to within the 600 metre buffer zone allocated by the Metropolitan Regional Planning Scheme. The Management Plan has been prepared to satisfy Condition 12-1 as specified in Ministerial Statement 755 (November, 2007).

 Alkimos Odour Management Plan
  

EPA Bulletins (Advice to Minister for Environment)

The EPA advice to the Minister for the Environment was published in Bulletins 1238 (Site A) and 1239 (Site B) on November 13 2006.

 Bulletin 1238 Site A
  
 Bulletin 1239 Site B
  

Public Environmental Review

 Invitation to make a submission
  
 Executive Summary
  
 Complete PER - (for Adobe PDF Reader version 4 and above)
  
 Complete PER - (for Adobe PDF Reader version 7)
  

PER - Individual Document Sections

 Table of Contents and Executive Summary
  
 01 - Introduction and Overview
  
 02 - The Proposal
  
 03 - Existing Environment
  
 04 - Environmental Impact and Management Strategy
  
 05 - Consultation
  
 06 - Specific Environmental Factors - Site A
  
 07 - Specific Environmental Factors - Site B
  
 08 - Environmental Management
  
 09 - References
  
 10 - Glossary
  
 Appendix A - Draft Alkimos Ocean Outlet EMP
  
 Appendix B - Map Plans for Alkimos Wastewater Treatment Plant Project
  
 Appendix C - Atteris Final Report
  
 Appendix D - Community Consultation - Evaluating Attitudes Towards Alkimos
  

Environmental Scoping Document

 Environmental Scoping Document
  
 Environmental Scoping Document - Figures
  
 EPA Approval and Comments
  

Odour Reports

Reports addressing odour dispersion modelling and investigation of the odour 'ponding' phenomenon.

 Buffer Zone Report - CEE Pty Ltd
  
 Alkimos Emissions and Dispersion Report - CSIRO
  
 Alkimos Emissions and Dispersion Report : Supplementary Material - CSIRO
  
 Alkimos Emissions and Dispersion Report - CEE Pty Ltd
  

Flora and Fauna Reports

 Fauna Assessment
  
 Flora and Vegetation Assessment
  
 Flora and Vegetation Assessment - Figures
  

Geoheritage Reports

These reports describe the geoheritage values in the wider Alkimos regional context, specifically in relation to the parabolic coastal dune systems. No further work is anticipated for this factor.

 Assessment of the Alkimos coastal area : Stage 1 - the onshore areas
  
 Important geological sites in the Perth and Southwestern area of Western Australia
  

Hydro and Geotechnical Reports

 Hydrogeological Investigations
  
 Preliminary Materials Assessment for Site B - Coffey Geosciences
  

Marine Reports

The Reports Labelled as Final were baseline studies for the completion of the Public Environmental Review.  The Reports labelled as Interim are ongoing baseline studies that require further data to be collected before they can be finalised.  Once the interim reports are completed they will be made available on this website for your viewing as final reports.  If further marine baseline studies are required they will also be made available as soon as the reports have been completed.

 Benthic Habitat Mapping - Final
  
 Currents and Wave Studies - Final
  
 Groundwater - Final
  
 Hydrodynamic Modelling - Final
  
 Phytoplankton Surveys - Interim
  
 Sediment Surveys - Final
  
 Water Quality Characterisation - Interim
  

Bibliography

 Alkimos Bibliography
  

 


The Alkimos Wastewater Treatment Plant is to be located in the Alkimos-Eglinton area in the north-west corridor. This area is subject to a Metropolitan Region Scheme amendment (1029/33). Environmental documentation relevant to the MRS amendment within the region may be found at http://www.planning.wa.gov.au/The+planning+system/Region+schemes/default.aspx#MRS (go to Regional Scheme Amendments and select Amendment No. 1029/33).

Amended Project Referral

(superseded by Environmental Scoping Document)

 Alkimos Referral Document
  
  Alkimos s38 Questionnaire
  
 Figure 1-1 Alkimos Wastewater System Catchment Boundary
  
 Figure 1-2 Alkimos WWTP Investigated Locations
  
 Figure 1-3 Alkimos Wastewater Treatment Plant Sites A,B and B1
  
 Figure 2-1 Alkimos Wastewater Treatment Plant Staged Layout (Conceptual)
  
 Figure 2-2 Alkimos Wastewater Treatment Plant Conceptual Layout of Ocean Outlet
  
 Figure 2-3 Alkimos Wastewater Treatment Plant Proposed Layout of On-site Infiltration