Works have commenced in Quinns Rock 4E, as part of the statewide Infill Sewerage Program. This will enable you to connect your property to Water Corporation’s central wastewater system.
We hope to finish construction work by July 2012, however work associated with many houses will be finished long before then. While minor delays are possible due to weather or challenging ground conditions, we are aiming to get the job done as quickly as possible and with minimal disruption.
While construction of a central wastewater system is quite disruptive, we aim to minimise the impact on you and your property.
The construction of a central wastewater system requires the excavation of trenches between 2-5 meters deep. This is likely to create some sand and dust, but we will do all we can to keep the area as tidy as possible and clean up as we go.
Should works be undertaken within your property we will do our best to restore it to as near as practicable to its original condition.
| Quinns Rock 4E information sheet - May 2011 | |
| View a map of Quinns Rock 4E project area | |
Works have commenced in Quinns Rock 8A and 9A, as part of the statewide Infill Sewerage Program. This will enable you to connect your property to Water Corporation’s central wastewater system.
We hope to finish construction work by April 2013, however work associated with many houses will be finished long before then. While minor delays are possible due to weather or challenging ground conditions, we are aiming to get the job done as quickly as possible and with minimal disruption.
While construction of a central wastewater system is quite disruptive, we aim to minimise the impact on you and your property.
The construction of a central wastewater system requires the excavation of trenches between 2-5 meters deep. This is likely to create some sand and dust, but we will do all we can to keep the area as tidy as possible and clean up as we go.
Should works be undertaken within your property we will do our best to restore it to as near as practicable to its original condition.
| Quinns Rock 8A and 9A information sheet - February 2012 | |
| View a map of Quinns Rock 8A project area | |
| View a map of Quinns Rock 9A project area | |