Project goal:

To improve the reliability of water supply to the Yanchep area.

Status:

Completed

Delivery Date:

December 2020

What’s happening?

We’ve recently finished installing 2 kilometres of water pipeline along Marmion Avenue, between Cinnabar Drive and Revolution Avenue, to cater for continued growth and improve the reliability of water supply to the Yanchep area. 

The work included:

  • Construction of a 700mm nominal diameter water main approximately 2km long
  • Pipework connections complete with valves and fittings

Where is this happening?

Please refer to the project map for the location of the work.

When is this taking place?

Construction began in July 2020 and is now complete.

How will this impact the community?

We understand that there has been a lot of construction work in the area due to development, so we have appreciated your patience and understanding as we completed this essential work.