Navigate home logo

Project goal:

Construct new pipeline to improve the reliability of water supply for current and future developments in Wandi, within the City of Kwinana.

Status:

In construction

Delivery date:

Construction began early March 2024 and expected to finish mid-2024.

What is happening?

Water Corporation's authorised contractor, Rob Carr, will install the replacement 2.3 kilometres of distribution water main along Lyon Road, Wandi.

This will include: 

  • Removal of the current PVC pipe
  • Installation of new steel water pipe
  • Reinstatement of affected areas

This water main will be below-ground and installed using open trench excavation. It is part of our long term plan to ensure we can provide security of water supply and meet increased water demand in the southern metropolitan area

Project background

The purpose of the pipeline along Lyon Road is to cater for future growth in Wandi and the City of Kwinana. The existing PVC pipe, installed in 2020, has structural deficiencies and was not connected. Therefore, the construction work to remove and replace this pipe will not impact water supply.

Where is this happening?

The new pipeline will run from Honeywood Avenue to Cassowary Chase in Wandi. Please see the below map.

  

When is this taking place?

Work began early March 2024 and is expected to take six months to complete.

Most of this work will take place Monday to Friday between 7 am and 7 pm. However, some work may be required on a Saturday between 7 am and 3 pm.

How will this impact the community?

Traffic disruptions
To ensure work is completed safely, traffic management and detours will be in place along Lyon Road to help direct traffic around the work area.

Construction activity
As with any construction work there will be an increase in noise, dust and activity in the area. We will aim to reduce these impacts where possible.

Saturday work
Although most work will occur during the week, some work may be required on a Saturday to ensure work is completed within the required timeframe. We will endeavour to keep this to a minimum and adhere to a noise management plan approved by the City of Kwinana.

Property access
If your driveway access is temporarily impacted due to construction or safety reasons, Rob Carr will work with you in advance to discuss alternative arrangements.

Restoration
Once new pipe sections are in the ground, all open trenches will be progressively backfilled, compacted and reinstated. 

We follow a thorough restoration process to ensure all impacted areas are replaced like for like, where practically possible. We work closely with the City of Kwinana and residents to ensure all reinstatements are carried out to an acceptable and high standard.

Water Supply
The current PVC pipeline has never been connected to the water network. Therefore, the construction work to remove and replace this pipe will not impact water supply. 

Once the new pipe has been installed, a temporary water interruption will be required to connect it to our existing infrastructure. This is expected to take a few hours and will be arranged during off peak water usage times. Notification will be sent to those impacted closer to the date.

We thank you for your patience and appreciate your cooperation while this essential work is carried out.

How do I stay informed?

To stay up to date on the project, sign up to our mailing list or watch out for project updates on this page.
Sign up

 

Taylor O’Dea - Community Engagement Advisor

Subscribe for project updates