Wandi - new water pipes
Project goal:
Construct new pipeline to improve the reliability of water supply for current and future developments in Wandi, within the City of Kwinana.
Status:
In construction
Delivery date:
Construction began early March 2024 and expected to finish mid-2024.
What is happening?
Water Corporation's authorised contractor, Rob Carr, will install the replacement 2.3 kilometres of distribution water main along Lyon Road, Wandi.
This will include:
- Removal of the current PVC pipe
- Installation of new steel water pipe
- Reinstatement of affected areas
This water main will be below-ground and installed using open trench excavation. It is part of our long term plan to ensure we can provide security of water supply and meet increased water demand in the southern metropolitan area
Project background
The purpose of the pipeline along Lyon Road is to cater for future growth in Wandi and the City of Kwinana. The existing PVC pipe, installed in 2020, has structural deficiencies and was not connected. Therefore, the construction work to remove and replace this pipe will not impact water supply.
Where is this happening?
The new pipeline will run from Honeywood Avenue to Cassowary Chase in Wandi. Please see the below map.
When is this taking place?
Work began early March 2024 and is expected to take six months to complete.
Most of this work will take place Monday to Friday between 7 am and 7 pm. However, some work may be required on a Saturday between 7 am and 3 pm.
How will this impact the community?
Traffic disruptions
To ensure work is completed safely, traffic management and detours will be in place along Lyon Road to help direct traffic around the work area.
Construction activity
As with any construction work there will be an increase in noise, dust and activity in the area. We will aim to reduce these impacts where possible.
Saturday work
Although most work will occur during the week, some work may be required on a Saturday to ensure work is completed within the required timeframe. We will endeavour to keep this to a minimum and adhere to a noise management plan approved by the City of Kwinana.
Property access
If your driveway access is temporarily impacted due to construction or safety reasons, Rob Carr will work with you in advance to discuss alternative arrangements.
Restoration
Once new pipe sections are in the ground, all open trenches will be progressively backfilled, compacted and reinstated.
We follow a thorough restoration process to ensure all impacted areas are replaced like for like, where practically possible. We work closely with the City of Kwinana and residents to ensure all reinstatements are carried out to an acceptable and high standard.
Water Supply
The current PVC pipeline has never been connected to the water network. Therefore, the construction work to remove and replace this pipe will not impact water supply.
Once the new pipe has been installed, a temporary water interruption will be required to connect it to our existing infrastructure. This is expected to take a few hours and will be arranged during off peak water usage times. Notification will be sent to those impacted closer to the date.
We thank you for your patience and appreciate your cooperation while this essential work is carried out.
How do I stay informed?
To stay up to date on the project, sign up to our mailing list or watch out for project updates on this page.
Friday 23 August 2024
On Tuesday 13 August, asphalt reinstatement was completed from Cassowary Chase up to Magenup Drive. The remaining sections are planned to be completed on Friday 6 September.
This work is subject to weather conditions and may need to be rescheduled.
To ensure the safety of our crew and the community, please continue to follow all traffic management in the area.
Friday 26 July 2024
Please be aware, detours will be moving and changing along Lyon Road throughout the week to accommodate our work.Please follow all traffic management in the area to ensure the safety of our crew and the community.
Tuesday 16 July 2024
To connect the newly installed pipeline to our existing infrastructure, a very small section of customers (approx. 6 properties) will have a temporary interruption to their water supply.
This work was planned to take place on Wednesday 17 July 2024, however it has now been postponed. Those impacted will receive a written notification to their letterbox to advise them of the new date, when it has been confirmed.
Detours will continue to be in place. Please follow all traffic management to ensure the safety of our crew and the community.
Friday 21 June 2024
Work continues to progress well; we expect to have all 2.3 kilometres of pipeline installed by the end of next week. Once completed, restoration of the area will begin.
From Monday 24 June 2024 access to Cassowary Chase from Lyon Road will be closed. Northbound traffic will be directed to use Sida Street. This is necessary for the completion of pipe installation work.
Detours will be in place during the restoration work. You may also notice other construction work in the area. Please follow all traffic management to ensure the safety of our crew and the community.
We follow a thorough process to restore all impacted areas as close as possible to their prior condition.
Thursday 2 May 2024
Work is progressing well; we have installed 600 meters of pipeline from Honeywood Avenue to Wandi Drive. From Monday 29 April until mid-May 2024, we plan to install a further 800 meters on Lyon Road from Wandi Drive to Magenup Drive.
Traffic management and detours will be in place along Lyon Road to ensure work is completed safely. You may notice other construction work and associated traffic management nearby. Please be cautious of increased activity near the work site.
Taylor O’Dea - Community Engagement Advisor