Mandurah Pebble Beach Boulevard

To secure and improve the supply of water services to the Meadow Spring area.

back to current projects

Project goal:

To secure and improve the supply of water services to the Meadow Springs area.

Status:

In construction

Delivery Date:

End of 2019

What’s happening?

Through our approved contractor, Avid Resources, will be installing 1.7 km of water main along Pebble Beach Boulevard, Meadow Springs in the City of Mandurah. We will be installing a 700mm diameter water supply pipeline, along varying alignment down Pebble Beach Boulevard. This work will improve the security of water supplied to customers in the Meadow Springs and Lakelands areas.

Where is this happening?

Work will be taking place along Pebble Beach Boulevard between Kirkland Way and Meadow Springs Drive. Work will occur in the road, to minimise impact on surrounding houses and public open space. We have taken this decision as alternatives would have had a higher impact on surrounding houses and in particular driveways, verges and footpaths.

Map of Pebble Beach works  - Mandurah

Why is this work taking place?

This project is part of a wider program of work to be undertaken in the North Mandurah area to address the increase in demand. Growth and development in areas such as Meadow Springs and Lakelands require us to make water infrastructure upgrades.

When is this happening?

Work will commence on 17 June 2019 and is expect to finish by the end of September 2019. You may see some increased activity in the area from 10 June, as services are identified within the road. Work will take place between 7am and 5pm, Monday to Friday. All work will be conducted by our approved contactor Avid Resources. We will keep customers updated as work progresses via this project page.

How will this impact the community?

Local residents in these areas should expect medium-level noise from trucks and an excavator laying pipework. There will also be some low-level vibrations and dust present.

We request that road verges be kept clear over this period, closest to the road reserve along the pipeline route. Access to drive ways may be temporarily blocked while the work progresses past properties. We will endeavour to give residents as much notice as possible.

A one lane road closure will occur along Pebble Beach Boulevard as the project progresses. Throughout the duration of the work, traffic management will be in place along the pipeline construction route and road users will be asked to keep to the reduced speed limit, which will be indicated through signage in these areas. Please check our website for updated traffic management information.

We are mindful that many people put a lot of time and effort into their verges. If any trees, shrubs, or lawn needs to be removed, they will be replaced and the area restored. If driveways or paving are disturbed they will also be restored and reinstated. We have taken the decision to construct in the road to avoid as much disturbance as possible. We will complete reinstate of the road as work progresses, in agreement with the City of Mandurah, to minimise disruption.

Who can I contact?

For more on the project, please email emmanuel.botsoie@watercorporation.com.au or on (08) 94202968.

For all community related enquiries, please contact Jen Woollard on jen.woollard@watercorporation.com.au or call (08) 9420 2651.

For after hours assistance please contact our 24 hour Faults, Emergencies and Security line on 13 13 75.

Work has commenced on the Pebble Beach Boulevard water main project. Our approved contractor Avid Resources commenced construction work on 17 June 2019.

Two work teams will be completing work at the same time along the pipeline. The decision to operate two teams has been made to help reduce the length of the projects impact on residents and the local community.

The maps below show where each team will be starting their work, and where traffic management will be in place. The tables below have date information for road closures.

Please make sure to follow the traffic management and detour signs closely. We have had multiple reports of residents driving the wrong way down Pebble Beach Boulevard to avoid detours. If you notice this happening, please report to local WA Police on 131 444. We've already reported the issue, along with the City of Mandurah, to the police.

Residents bins will be moved to allow for collection, with our contractor moving them back once collection has occurred.

Pebble Beach Boulevard is being temporarily reinstated as work progresses. This enables the road to be reopened as soon as the construction crews move on. Final road reinstatement will be completed at the end of the project, and we will endeavour to restore everything to as close to original condition as possible. This process will be completed in conjunction with the City of Mandurah.

As work progresses, you will be informed if your property access will be impacted by our contractors. If you are not home when we try to contact you, a notification will be left in your letterbox. We will try to keep access open for as long as possible, and will assist to ensure access remains possible where practicable.

Work Team 1 – Starting at Meadow Springs Drive & Pebble Beach Boulevard

Work Team 1- Stages Road closures Dates
Stage 3  Camden Lane/Greenville Vista - Windcrest Way 14 August - 6 September 
Stage 4  Camden Lane - Grandmere Parade 11 - 13 September

 Map showing Pebble Beach works - Team 1 - Stage 3 and Stage 4

Work Team 2 – Starting at Windcrest Way & Pebble Beach Boulevard

Work Team 2- Stages Road closures Dates
Stage 2 Grandmere Parade - Brookdale Way (South) 16 August - 2 September
Stage 3 Brookdale Way (South) - Newbridge Street 3 - 16 September
Stage 4 Bramshaw Street - Kirkland Way 17 - 23 September

 Map showing Pebble Beach works - Team 2 - Stage 3 and Stage 4

Quarry Park

For access to Quarry Park, please use alternative access roads and utilise parking that is available. Rushcliffe Way and Grandmere Parade will be used as detour routes, and we suggest accessing the park from these roads and utilising available parking. Pebble Beach Boulevard will be closed in front of the Park, and therefore vehicle access is restricted. The below map indicates alternative access routes and street parking that can be found around Quarry Park.

Map of works taking place at Quarry Park - Pebble Beach Boulevard water main project

 

Stay up to date with the project. Email us your details and we'll add you to our mailing list.

sign up


back to current projects