Maintenance work to wastewater scheme in Mundaring

back to current projects

Project goal:

Bury a wastewater pipe deeper underground to protect the asset.

Status:

Commencing soon

Delivery Date:

19 February 2018 to 4 March 2018

What's happening

We will be burying one of our existing pipes further underground to provide greater protection for the asset, which connects to the Mundaring Wastewater Treatment Plant.

A 60 metre section of the existing pipe along Helena Street will be sunk by approximately 600 millimetres. This will involve potholing, digging and excavating to re-lay the pipe, followed by backfilling of the pipe trench and final reinstatement.

A new air valve and pit will also be installed at the intersection of Helena Street and Hartung Street in Mundaring, nearby this work. This valve will be installed three metres off the road at this intersection. 

Community benefits

  • Protecting our wastewater assets in Mundaring

Community impacts

During stage one of this work, Helena Street is expected to be closed 24 hours a day, with traffic management in place from Monday 19 February to Sunday 25 February 2018. Property access will be maintained for residents living along Helena Street, however this road will be closed to outside traffic over this period.

During stage two of this work, Helena Street will be re-opened. Traffic management will still be in place at the intersection of Helena Street and Hartung Street, with local road users asked to travel slower in this work area. Traffic management and signs will be place until Sunday 4 March 2018.

Timing

The work will be completed between Monday 19 February 2018 and Sunday 4 March 2018.

More information

Please contact Senior Community Engagement Advisor, Kristy Lind, on kristy.lind@watercorporation.com.au or call (08) 9420 2570.