Perth & West Perth Relining

back to current projects

Project goal:

Refurbish ageing wastewater pipes in Perth and West Perth

Status:

Complete

Delivery Date:

March 2018
 

What's happening?

In February 2018, Water Corporation began work in West Perth and Perth to refurbish ageing wastewater pipes. Sewer relining work is carried out using trenchless technology to clean access chambers and refurbish existing wastewater pipes.

Where?

Fitzgerald Street, West Perth

Work began in mid February and took 2 weeks to complete. It started from the Robertson Park Tennis Centre and progressed across Fitzgerald Street to the WA Italian Club carpark (refer to map).

Mick Michael Park, West Perth 

Work began in early March and took 1 week to complete. It took place within Mick Michael Park on the corner of Charles and Violet Streets (refer to map).

Night work began Monday, 19 March and took 1 week to complete.  Work started from Violet Street progressed through Mick Michael Park and continued along Charles Street.

Perth CBD

Work began in late February and was completed by late March. It took place in sections along Mounts Bay Road, Spring Street, Irwin Street and Sherwood Court (refer to map).

Wellington and Pier Streets, Perth

Night work began in early March and took 2 weeks to complete. It took place from the Wellington and Barrack Street intersection and continued along Pier Street (refer to map).

Market and Sutherland Streets, West Perth

Night work began mid-March and took 2 weeks to complete. Work took place near the Watertown Brand Outlet Centre on Sutherland Street and continued along Market Street (refer to map). 

Access to part of the Fremantle line cycle path was temporarily unavailable during this section of work, with detours in place to direct cyclists and pedestrians to shared use paths on Market and Railway Streets.

Charles Street and Beatty Park, North Perth (Bypass)

As part of the sewer relining work, the installation of a wastewater bypass pipe was required to avoid wastewater overflows. Two excavations were required to create a bypass on Charles Street to progress sewer relining work, these where located within a fenced off area in Beatty Park on the Charles Street side.

Day work began in early March and took 2 weeks to complete.

Night work began Monday, 19 March and took 1 week to complete. Work commenced from Violet Street, progressed through Mick Michael Park and continued along Charles Street.

Map of the sewer relining work areas in the City of Vincent.

The red lines in the map below are the pipes to be relined.

We generally work around the access chambers shown as red dots on the map.

Map of work areas in West Perth

 

Map of the sewer relining work in the City of Perth 

The red lines in the map below are the pipes to be relined.

We generally work around the access chambers shown as red dots on the map.

Perth CBD

Perth CBD sewer relining work areas

 

 

Sutherland and Market Streets, West Perth

Market St sewer relining work

 

Wellington and Pier Streets

Wellington St sewer relining work

 

If you have any queries please contact one of the following people:

Interflow Project Manager, Steve Thompson on 0407 157 056 (24 hours)

Water Corporation Project Manager, Janarthan Ganesh on (08) 9420 2178 (office hours)