Metropolitan residential - Pipes for Perth

Project goal:

To renew around 22 kilometers of ageing water mains across 9 Local Government Authorities.

Delivery date:

July 2019

What's happening?

In March 2019 we began work to renew around 22 kilometres of ageing water mains across numerous streets in the Perth metro area.

Work will take place in a staged approach across 9 Local Government Authorities. All customers to be impacted will receive prior notification detailing when work will be taking place along their street.

This work will help secure the reliability of water supply to customers in these areas for decades to come.

Where is this happening?

Replacement of the ageing water mains will take place across the City of Stirling, City of Bayswater, City of Swan, City of South Perth, City of Nedlands, City of Belmont, City of Joondalup, City of Melville and City of Gosnells.

Please see 'Project stages and schedule' tab for a full list of streets to be renewed.

Why is this taking place?

The ageing mains require replacement as we believe they are likely to fail.

The replacement of these pipes will help secure the reliability of water supply to customers in these areas for decades to come.

When is this happening?

The full project will run between March and July 2019. For the start dates and duration of impact for each street, please see the 'Project stages and schedule' tab.

Who to contact?

See the 'Project Stages and Schedule' tab and find your street to see who to call for immediate action on site:

Valmec Project One - Project Manager Michael Blesic on 0456 891 192

Valmec Project Two - Project Manager Eddie Erasmus on 0448 526 031

Civcon - Project Manager Daen Gould on 0415 068 245

For general project related enquiries:

Pipes for Perth - (08) 9420 3529 or pipesforperth@watercorporation.com.au

How will this impact the community?

Construction fencing will be erected along your street, driveways may be restricted at times, traffic management and detours will be in place, the area will experience an increase in noise and traffic.

Contact us

  • For general enquiries please email: pipesforperth@watercorporation.com.au or phone: (08) 9420 3529.

For immediate action on site, contact details can be found at the bottom of this page. Check the Project package column to find the relevant contact for works in your street.

Construction schedule for each street, last updated 29 May 2019:

Suburb Street Project package Start date

Duration
(weeks)

Balcatta Cedric Street South Civcon Late May 3
Balcatta  Eversley Street and
Delafield Way
Valmec Two Early June 6
Balcatta  Jedda Road and
Dusting Road
Civcon Early June 5
Bayswater King Street Civcon Mid May 3
Bedford Birkett Street Valmec One  COMPLETE COMPLETE
Bedford Salisbury Street Valmec One COMPLETE COMPLETE
Bedford The Strand Valmec One Early April
Carine Holmesfield Crescent Valmec Two Early June 1
Doubleview  Ravenscar Street Valmec One Early May 10
Duncraig Kelvin Road Valmec Two Early June 5
Gwelup Wanstead Street Civcon Late April 4
Hamersley Eglington Crescent Valmec One Mid May 6
Inglewood Wood Street Valmec One COMPLETE COMPLETE
Innaloo Langley Crescent Valmec One COMPLETE COMPLETE
Innaloo Bates Road Valmec One COMPLETE COMPLETE
Maddington Aldington Street Civcon Mid June
Manning Henning Crescent Valmec One Mid April 10 
Morley Old Collier Road Civcon Mid June 3
Morley Benara Road Valmec Two Early June 7
Myaree North Lake Road Valmec Two Mid June 5
Nedlands  Burwood Street and
Verdun Street
Valmec One Early May 8  
Nollamara Myimbar Way Valmec Two Late April 4
Nollamara Montrose Way and
Montrose Street
Civcon Mid June 5
North Beach Giles Street Valmec Two Early June
North Beach Muller Street Valmec Two Mid June 3
North Beach Rona  Street Valmec Two Mid June 3  
Osborne Park Baden Street Valmec Two Late May
Osborne Park Donovan Street Valmec Two Late May 2
Padbury Warburton Avenue Civcon Mid May 4
Redcliffe Bulong Avenue Valmec Two Late April
South Guildford Kidman Avenue Valmec One Early April 9  
Stirling Cedric Street North Civcon Late April
Stirling Bryan Place Valmec Two Early May
Tuart Hill Eldorado Street Valmec One Early April 8  
Tuart Hill Lawley Street Valmec One Mid May 7  
Tuart Hill Fagan Street Valmec One Early June 4  
Tuart Hill Federal Street Valmec One Early June
Tuart Hill Wattle Street Valmec One Mid April
Tuart Hill York Street Valmec One Mid April 9
Warrick Dorchester Avenue Civcon Early June
Watermans Bay Elsie Street and
Ethel Street
Civcon Early June
Yokine Douglas Avenue Civcon Mid May 3  

Who to contact?

Valmec Project One - Project Manager Michael Blesic on 0456 891 192

Valmec Project Two - Project Manager Eddie Erasmus on 0448 526 031

Civcon - Project Manager Daen Gould on 0415 068 245

For general project related enquiries:

Pipes for Perth - (08) 9420 3529 or pipesforperth@watercorporation.com.au