Clarkson wastewater pipeline

Constructing a new wastewater pipeline in Clarkson to extend the wastewater network in the northern corridor.

back to current projects

Project goal:

Construct a new wastewater pipeline in Clarkson to extend the wastewater network in the northern corridor of metropolitan Perth.

Status:

In design

Delivery Date:

2020-2021

Documents & Downloads

What's happening?

To cater for growth and the disposal of wastewater flows in the northern corridor of metropolitan Perth, Water Corporation proposes to construct the following work in Clarkson and Neerabup:

• Installation of 2kms of 1800-2200mm diameter wastewater main
• Installation of eight access chambers

This work will take place at the intersection of Connolly Drive and Walyunga Boulevard, through the Clarkson TAFE car park, towards Harmony Avenue, south along Hannaford Avenue, across Homestead Park, east along La Mirada Avenue, under the Mitchell Freeway and east along Hall Road in Neerabup. See project map below.

Once complete, the pipeline will play a vital role in transferring wastewater flows from multiple wastewater pump stations and onto the Alkimos Wastewater Treatment Plant.

Project timeline

2017: Commenced early investigation works for pre-design and started working closely with project key stakeholders including the City of Wanneroo.  

2018: Completed draft design and started the formal approvals processes including in consultation with Department of Water and Environmental Regulations.

2019: Impacted customers will have the opportunity to provide comment on the project. Public comment period is open from 20 March to 12 April 2019. See the notice of proposal document on this page for more information. Rest assured, the community engagement team will continue to work closely with local residents and the community leading up to and throughout project delivery.

The project team will engage a contractor to finalise the project design and undertake construction work.

2020-2021: Construction work is scheduled to start in mid-2020 and is expected to take about ten to twelve months to complete.

Project map

   

redline Pipeline route    

Contact us

For more information, please contact Senior Advisor - Community Engagement, Jess Moloney-Christie via email Jess.Moloney-Christie@watercorporation.com.au.