Town of Cambridge Relining

Refurbish ageing wastewater pipes in Town of Cambridge

back to current projects

Project goal:

Refurbish ageing wastewater pipes in Town of Cambridge

Status:

In construction

Delivery Date:

July 2019

What's happening?

 

Water Corporation will refurbish ageing wastewater pipes in Floreat, City Beach, Wembley and Wembley Downs from March - July 2019. Refer to the second tab above for work areas within the Town of Cambridge.

Sewer relining uses trenchless technology to clean access chambers and refurbish existing wastewater pipes.

What are the impacts? 

Residents may notice more activity in the area, noise from generators and vehicles and temporary odour. If access to your property is required the contractor, Interflow, will contact you directly to discuss and arrange entry. Where required, traffic management will be in place to direct people safely around the work area. 

When?

 

Floreat

 

Work will begin in Floreat in mid-March 2019 and is expected to be completed by April 2019.

Work will take place in the vicinity of Oceanic Drive - refer to the second tab above for  a map of the work area. 

We will work from Monday to Saturday between 7am and 5pm, as approved by the Town of Cambridge. Some night work will be required. We will notify nearby residents in advance when night work is scheduled. 

We will generally be in one area for 6 days at a time as we progress work along the wastewater route.

Oceanic Drive night work 

Night work will take place along Oceanic Drive between Louth Rd and Howtree Place from 8 - 12 April 2019 between 7.00pm and 6.00am. Traffic management will be in pace to safely direct vehicles around the work area. There will not be any full road closures. 

 

City Beach, Floreat and Wembley Downs

Work will begin in City Beach, Floreat and Wembley Downs in late-March 2019 and is expected to be completed by May 2019.

Work will take place in the vicinity of The Boulevard, Bold Park Dve, Elphin St, Oceanic Dve, Alderbury St and Meagher Dve - refer to the second tab above for a map of the work area. 

We will work from Monday to Saturday between 7am and 5pm, as approved by the Town of Cambridge. Some night work will be required. We will notify nearby residents in advance when night work is scheduled. 

We will generally be in one area for 6 days at a time as we progress work along the wastewater route.

 

Wembley and Floreat

Work will begin in Wembley and Floreat early April 2019 and is expected to be completed by June 2019

Work will take place in the vicinity of Pangbourne St, Jersey St, Alexander St, Simper St, Grantham St, Reserve St, Keane St, Ruislip St and Selby St  - refer to the second tab above for a map of the work area. 

We will work from Monday to Saturday between 7am and 5pm, as approved by the Town of Cambridge. Some night work will be required. We will notify nearby residents in advance when night work is scheduled. 

We will generally be in one area for 6 days at a time as we progress work along the wastewater route.

 

Property gas traps and access chamber cover replacement  work 

As part of this work, we will also replace ageing property gas traps and access chamber covers.

While this work will have minimal impact on the community, you may notice increased activity in the area and temporary odour within a few metres of the work area.

If access to your property is required, Interflow will try to contact you directly to discuss the work and arrange entry. Please note we will not need to enter your home.

 

Map of work areas

The red lines in the maps below are the pipes to be relined.

We generally work around the access chambers shown as red dots on the map.

 

Floreat 

Sewer relining Floreat

City Beach, Floreat and Wembley Downs

sewer relining Perry Lakes

Wembley and Floreat 

Sewer relining Grantham

If you have any queries please contact one of the following people:

 

Steve Thompson, Interflow Project Manager, on 0407 157 056 (24 hours)

Gary Gilmore, Water Corporation Project Manager, on (08) 6330 6744 (office hours)

Karolina Romeo, Water Corporation Community Engagement Advisor, on (08) 9420 2010 (office hours)

 