Baldivis wastewater upgrades
Project goal:
We are upgrading the wastewater infrastructure in Baldivis to cater for the growing community and future land development.
Status:
In construction
Delivery:
Late 2024
What’s happening?
- a new below ground wastewater pump station
- overflow storage
- two short sections of wastewater pipeline.
Where is this happening?
Work is taking place off Stillwater Drive in Baldivis. Please refer to the map below.
Construction vehicles will be entering and exiting the site via Stillwater Drive and Magenta Crescent throughout the work.
Why is this taking place?
The Baldivis area is currently experiencing high growth in residential land development, which requires new and upgraded infrastructure to service the growing community.
When is this taking place?
Our contractor, BMD Construction, started work in late September 2022. Work is expected to be completed in late 2024.
Most of the construction work will be completed Monday to Saturday between 7 am and 7 pm. However, some night and Sunday work will be required, but we will endeavour to keep it to a minimum.
How will this impact the community?
Due to the environmental sensitivities around the work area, we are working with the Department of Water and Environmental Regulation (DWER), the City of Rockingham and our environmental team, to minimise any potential impact during and after construction.
Noise and dust
There will be an increase in noise, dust and activity in the area. We will work closely with the City of Rockingham and the community to minimise any impacts.
Traffic management
There will be temporary impacts to roads and pedestrian paths. For the safety of the contractors and the community, traffic management will be in place as needed. Please follow the signs and drive safely.
Reinstatement
We follow a thorough reinstatement process to ensure all impacted areas are replaced like for like, where practically possible. We will also work closely with the City of Rockingham and residents to ensure all reinstatements are carried out to an acceptable and high standard.
Tuesday, 27 August 2024
An early morning start is required to continue the work of connecting the new structures to the existing infrastructure. 5 am – 7 pm Tuesday, 27 August 2024Traffic management will be in place near the site to help direct the tanker trucks that will be used to manage the flow of wastewater during this period.
To ensure the safety of our crew and the community, please continue to follow all traffic management in the area.
Tuesday, 6 August 2024
To help minimise disruption to the community, another night of work will take place during off peak wastewater usage times. Overnight from 7 pm Tuesday, 6 August to 7 am Wednesday, 7 August 2024.Please note another night will also be required to complete the connections.
This work is not expected to impact your water or wastewater services. Should a planned outage be required, those impacted will be notified in advance.
Tuesday, 16 July 2024
We will be excavating an area at the Stillwater Drive and Magenta Crescent site to allow us to connect the pump station to our existing infrastructure. Tanker trucks will be used to manage the flow of wastewater in the area during this period.
To help minimise disruption to the community, work will take place during off peak wastewater usage times. Overnight from 7 pm Tuesday, 16 July to 7 am Wednesday, 17 July 2024
Nearby residents may notice increased truck activity in the area with stop/slow traffic management in place.
This work is not expected to impact your water or wastewater services. Should a planned outage be required, those impacted will be notified in advance.
February 2024
The team has recently completed construction of the new below ground 3000 KL wastewater storage tank. As this work required over 1200m3 of concrete, you may notice that truck activity on Stillwater Drive will be reduced.
In the coming months work will focus on constructing the underground pump station.
August 2023
The next phase of construction involves several concrete pours. These will occur over the next few months. Most of this work will be completed within the current schedule, Monday to Saturday between 7 am and 7 pm. However, one large concrete pour is required to be completed outside of these hours and is currently scheduled to take place 6 am to 7pm Saturday, 26 August 2023.
During this work, nearby residents may notice increased truck movements and activity around the work area. We will aim to keep the disturbance to a minimum as best we can. Concrete trucks will be arriving via Magenta Crescent and leaving the work site onto Stillwater Drive.
May 2023
We have created a large watertight area underground where we can install the new pumping station. We are now pumping the excess water out of the ground to allow the safe construction of our underground infrastructure. This is called dewatering.
The dewatering pumps need to run day and night, 7 days a week to keep the ground dry enough to work, while we install most of the underground infrastructure.
The pumps might generate some noise, but we trust this will be minimal. We have placed the pumps behind a tree canopy and we will have noise mitigation measures in place to minimise the risk of inconvenience. You can contact us with any questions.
November 2022
The site has been setup and some work has begun within the temporary fencing. We will begin major construction activities in early November. This will include:
Dewatering: pumping our the excess groundwater to keep the site safe to build on.
Piling: creating a watertight underground structure to accommodate the new pumping station.
August 2022
Ground surveys will take place over the next week with construction planned to start in early September.
Taylor O’Dea - Community Engagement Advisor