Ellenbrook to Wangara wastewater pipeline
Project goal:
We are upgrading the wastewater infrastructure to cater for the continued growth within the City of Swan and City of Wanneroo.
Type of project:

New wastewater pipeline
This project is part of the City of Swan water upgrades
Status:
In construction
Delivery Date:
Mid 2026
What’s happening?
We are installing a 6 km of single wastewater pipeline and 8.2 km of dual wastewater pipeline to cater for the continued growth within the City of Swan and City of Wanneroo.
Where is this happening?
This pipeline will extend from the existing Barrambie Way wastewater pump station in Henley Brook and connect to the existing wastewater network in Madeley. Please refer to the project map for the location of the pipeline.
When is this taking place?
Construction commenced in August 2024 and is estimated for completion in mid 2026.
How will this impact the community?
As with any construction activities there will be an increase in noise, dust and activity in the area. There will also be temporary impacts to roads, verges and pedestrian paths.
We will keep the community updated as the project progresses and be in touch before construction commences in your area.
As a short section of the pipeline will be installed through the Gnangara Pines. We have worked closely with the Department of Biodiversity, Conservation and Attractions (DBCA), the City of Swan and our environmental team, to minimise any potential impact to the area during and after construction.
We follow a thorough reinstatement process to ensure all impacted areas are replaced like for like, where practically possible. We will also work closely with the City of Swan, City of Wanneroo, businesses and residents to ensure all reinstatements are carried out to an acceptable and high standard.
Vision Street: July 2025
What is happening?
Work will soon commence to install the new wastewater pipeline along Vision Street (between Inspiration Drive and Old Gnangara Road).
To allow us to safely complete this essential work, staged partial road closures will be in place along the Southbound lane on Vision Street. The Northbound lane will remain open throughout our work. This is highlighted in the map below.
When is this happening?
Work will commence on 7 July and is expected to be complete by end of July 2025.
Work will be completed from 7pm to 5am, Monday to Saturday.
Atwell Street and Old Gnangara Road crossing: July 2025
What is happening?
Work will soon commence in two stages:
Stage 1
From 14 July, work will commence at the Atwell Street/Gnangara Road intersection (next to the roundabout) to install the new wastewater pipeline.
To allow us to safely complete this essential work, a small section of Atwell Street will be closed. This is highlighted in the map below (Map1).
Stage 2
From 25 July, work will commence to cross Old Gnangara Road to install the new wastewater pipeline. This work is expected to take 3 days of day and night work to avoid an extended road closure. Further details regarding this closure will be sent closer to the time. This is highlighted in the map below (Map 2).
When is this happening?
Stage 1 work is expected to commence from Monday 14 July for approximately 2 weeks.
Stage 2 work is expected to commence from Friday 25 July until Monday 28 July, once Stage 1 work is complete.
Work will be completed from Friday 7:00pm to Monday 5:00a.m.
Map of area:
Map 1
Map 2
What is Happening?
We will soon commence work to install the new wastewater pipeline from Alexandar Drive to Priest Road.
From Monday 30 June, new traffic detours will commence at the Alexandar Drive intersection and Gnangara Road to prepare for our day work. This includes:
- Closure of the southern westbound lane on Gnangara Road
- Opening of the new temporary median lane to continue traffic flow.
- Temporary closure of Huntington Parkway and detour through Coverwood Promenade.
- Alexander Drive/Gnangara Road Traffic Signals Off and detours in place.
When is this happening?
- From Monday 30 June, new traffic detours will commence at the Alexandar Drive intersection and Gnangara Road (between Tonkin Hwy and Mirrabooka Avenue).
- From Monday 7 July, day work will commence on Gnangara Road, between Alexander Drive and Priest Road to install a new wastewater pipeline.
This work is expected to be complete by end of October 2025 from Monday to Saturday, 7:00am to 5:00pm.
To avoid traffic disruptions, please consider using an alternate route when planning your journey.
Night work on Gnangara Road: April - June 2025
What is happening?
Night work will soon commence on Gnangara Road, between Alexander Drive and Priest Road to create a temporary new traffic lane. See map below for more detail.
This new lane will be essential to continue traffic flow along Gnangara Road once we commence work mid-2025 to install the new wastewater pipeline along Gnangara Road.
When is this happening?
• Construction of the replacement lane will begin Monday 28 April 2025 for approximately eight weeks.
• Work will be completed from 7pm to 5am, Monday to Saturday.
Success Way: April - July 2025
Construction has commenced on Venture Loop and Success Way. See a map of the work area below.
What to expect during construction:
- Single lane road closure: A single lane closure will be in place throughout the duration of work, traffic management and personnel will be onsite to safely re-direct traffic.
- Street & verge parking: Please avoid parking vehicles within the road or verge while work is being completed, to allow a safe work area for our crew and the community.
- Noise, dust, and vibrations: Noise, dust, and vibrations will be kept to a minimum, however, construction will involve road cutting, excavating, and compacting.
- Work hours: Work will be completed Monday to Friday, 7am to 5pm, and Saturdays as required. We will notify you again if we are required to work outside of these hours.
- Restoration of impacted areas: All areas impacted by the work, including verges and footpaths, will be returned to as close to their original condition as possible.
For local businesses
Let us know the vehicle access requirements and schedule of truck movements to and from your business by emailing Community Liaison Officer, Anastasia Puia at Enquiries-Barrambie@civconwa.com.au; or by calling 0434 124 892.
Map of work area
Pollino Gardens, Firmstone Circle and Priest Road: June to August 2025
What is happening?
Work will soon commence to install the new wastewater pipeline along Pollino Gardens and Priest Road.
To allow us to safely complete this essential work, we will temporarily close one lane on Pollino Gardens and redirect traffic through Firmstone Circle to continue traffic flow. This is highlighted in the map below.
When is this happening?
Work will commence in mid June and is expected to be complete by end of August 2025.
Work will be completed from 7pm to 5am, Monday to Saturday.
Map of area:





Ellenbrook to Wangara wastewater pipeline enquiries