Project goal: 

We are upgrading the wastewater infrastructure to cater for the continued growth within the City of Swan and City of Wanneroo.

Type of project:

Wastewater pipeline

New wastewater pipeline

This project is part of the City of Swan water upgrades

Status:

In construction

Delivery Date:

Mid 2026

What’s happening?

We are installing a 6 km of single wastewater pipeline and 8.2 km of dual wastewater pipeline to cater for the continued growth within the City of Swan and City of Wanneroo.

Where is this happening? 

This pipeline will extend from the existing Barrambie Way wastewater pump station in Henley Brook and connect to the existing wastewater network in Madeley. Please refer to the project map for the location of the pipeline.

overall map, wangara

When is this taking place?

Construction commenced in August 2024 and is estimated for completion in mid 2026. 

How will this impact the community?

As with any construction activities there will be an increase in noise, dust and activity in the area. There will also be temporary impacts to roads, verges and pedestrian paths. 

We will keep the community updated as the project progresses and be in touch before construction commences in your area.

As a short section of the pipeline will be installed through the Gnangara Pines. We have worked closely with the Department of Biodiversity, Conservation and Attractions (DBCA), the City of Swan and our environmental team, to minimise any potential impact to the area during and after construction. 

We follow a thorough reinstatement process to ensure all impacted areas are replaced like for like, where practically possible. We will also work closely with the City of Swan, City of Wanneroo, businesses and residents to ensure all reinstatements are carried out to an acceptable and high standard.

Night work on Gnangara Road: April  - June 2025

What is happening?

Night work will soon commence on Gnangara Road, between Alexander Drive and Priest Road to create a temporary new traffic lane. See map below for more detail.

This new lane will be essential to continue traffic flow along Gnangara Road once we commence work mid-2025 to install the new wastewater pipeline along Gnangara Road. 

When is this happening?

Construction of the replacement lane will begin Monday 28 April 2025 for approximately eight weeks.

Work will be completed from 7pm to 5am, Monday to Saturday. 

Success Way: April - July 2025

Construction has commenced on Venture Loop and Success Way. See a map of the work area below.

What to expect during construction:
  • Single lane road closure: A single lane closure will be in place throughout the duration of work, traffic management and personnel will be onsite to safely re-direct traffic.
  • Street & verge parking: Please avoid parking vehicles within the road or verge while work is being completed, to allow a safe work area for our crew and the community.
  • Noise, dust, and vibrations: Noise, dust, and vibrations will be kept to a minimum, however, construction will involve road cutting, excavating, and compacting.
  • Work hours: Work will be completed Monday to Friday, 7am to 5pm, and Saturdays as required. We will notify you again if we are required to work outside of these hours.
  • Restoration of impacted areas: All areas impacted by the work, including verges and footpaths, will be returned to as close to their original condition as possible.
For local businesses

Let us know the vehicle access requirements and schedule of truck movements to and from your business by emailing Community Liaison Officer, Anastasia Puia at Enquiries-Barrambie@civconwa.com.au; or by calling 0434 124 892. 

Map of work area

 

Mirrabooka Avenue & Pollino Gardens

What is happening?

Mirrabooka Avenue: We are installing pipe beneath Mirrabooka Avenue in Landsdale using tunnelling construction methodology. 2 tunnelling stations will be used to complete this work:

  • Station 1: located at the western end of Pollino Gardens
  • Station 2: located near the Gnangara Road and Mirrabooka Avenue roundabout

There will be no traffic impacts to Mirrabooka Avenue.

Pollino Gardens: During this time, we will also construct a temporary road connection between Pollino Gardens and Firmstone Circle in preparation for pipe installation on Pollino Gardens.

What to expect during construction:

Noise and dust: Noise, dust, and vibrations will be kept to a minimum however, construction will involve road cutting, excavating, and compacting.
Work hours: Work will be completed Monday to Friday, 7am to 5pm, and Saturdays as required. We will notify you again if we are required to work outside of these hours.
Restoration of impacted areas: All areas impacted by the work, including verges and footpaths, will be returned to as close to their original condition as possible. 

Map of work area 
 

 

Upcoming construction 

What is happening?

Work will soon commence work on Priest Road and Pollino Gardens. For the safety of our crew and the community, there will be no east-bound traffic on Pollino Gardens in the direction of Gnangara Road during this time. Traffic management will redirect traffic through Firmstone Circle to maintain flow.

  • Pollino Gardens: One lane will be closed and converted into a single lane road. 
  • Firmstone Circle: A temporary road access connection between Pollino Gardens and Firmstone Circle will be created by removing the verge area that currently separates these 2 roads.
  • Priest Road: During construction on Priest Road between Gnangara Road and Pollino Gardens, there will be no entry or exit to Gnangara Road. Alternate access can be found via Southmead Drive or Coverwood Promenade.
 
When is this happening?

Work on Priest Road and Pollino Gardens is expected to commence in mid 2025. Once we receive a confirmed start date, we will let you know. The expected duration of this work is approximately 4-6 weeks. 

How will this impact me?
  • Noise and dust: Noise and dust will be kept to a minimum however, construction will involve road cutting, excavating, and compacting.
  • Traffic flow: Traffic will be directed through Firmstone Circle to maintain traffic flow for the area.
  • Work hours: Work will be completed Monday to Friday, 7am to 5pm, and Saturdays as required. We will notify you again if we are required to work outside of these hours.
  • Restoration of impacted areas: All areas impacted by the work, including verges and footpaths, will be returned to as close to their original condition as possible. The temporary road access connection between Firmstone Circle and Pollino Gardens will be removed and reinstated.

 