Yanchep water and wastewater upgrades
Project goal:
To cater for new residential developments in northern Yanchep, we plan to construct 1.6km of water pipeline and a new wastewater pipeline.
Status:
Commencing soon
Delivery Date:
2025
What's happening?
Water Corporation are planning works to cater for population growth in Capricorn Estate and Yanchep City. We will construct approximately 1.6 km of 700mm diameter water distribution main along Marmion Avenue from Yanchep Beach Rd to Templetonia Boulevard. The proposed pipeline will connect to an existing pipeline near the intersection of Marmion Avenue and Yanchep Beach Road. We will also be constructing a new 1200mm diameter wastewater pipeline.
When is this happening?
At this stage, work is expected to commence in early 2025 and will take approximately 12 months to complete.
You may start to notice service location work prior to construction commencing.
Most of the work will be completed Monday to Friday between 7am and 5pm.
How will this impact me?
Residents may notice noise, dust, and increased vehicle activity in the area whilst we complete this work.
We will have a traffic management plan in place for sections as we install the new pipeline. We ask that you please follow our signage, to help ensure the safety of our work crews as well as the Yanchep and visiting community.
Joshua Olsen - Community Engagement Senior Advisor