Nannup Standby Bore
Project goal:
Water Corporation is constructing a new standby bore approximately 300 metres from the existing bore at the Thomas Road site in Nannup.
Status:
Construction complete
Delivery Date:
Late 2026.
What is happening?
Water Corporation is planning upgrades to the Warren–Blackwood Regional Water Supply Scheme over the coming years to improve its reliability and efficiency.
As part of this work, we have recently constructed a new standby bore at our Thomas Road site in Nannup, approximately 300 metres from the existing bore. Following testing, the new bore will remain offline until a future stage of the project, when it is connected to the water supply scheme.
We recently completed testing of the new standby bore. The final piece of work to complete is removal of the temporary settling pond that was used during construction.
the .
As part of this work, the crew will first remove the temporary fencing surrounding the pond and drain any residual water remaining in the basin. Once this has been completed, the liner will be removed before the area is backfilled and restored.
When is this happening?
Main construction work to construct, drill and test the bore is now competed.
The final work to remove the settling pond will be carried out by our contractor, Digga Civil, with work commencing Tuesday 10 November. We expect the work to take up to two weeks to complete.
Work will be undertaken between Monday and Sunday, 7:00am - 5:00pm. No night works are required.
- Work hours: Work will take place between 7:00am and 5:00pm, Monday to Sunday.
- Night work: No night work is required during work to remove the temporary settling pond.
- Construction: During work to remove the pond, you may notice some increased noise, vibration, and work vehicles on site.
We thank you for your patience and understanding while we complete this work.
Why is this happening?
The new standby bore will help support a reliable water supply for the region.
Once connected to the scheme, the new bore will operate alternately with the current one, enabling routine maintenance without service interruptions and providing a backup supply in the event of bore failure.
Following completion of testing, the standby bore will remain offline until a future stage of the project, when it is connected to the water supply scheme.
Community Engagement