Navigate home logo

Project goal:

Upgrade wastewater infrastructure in Glenfield Beach to help cater for growth in the area and improve the reliability of wastewater services in the City of Greater Geraldton.    

Status:

In Construction.

Delivery Date:

Mid 2024.

 

What's happening?

Water Corporation's authorised contractor, DM Civil, is working to upgrade the wastewater infrastructure in Glenfield Beach. This work will help cater for growth in the area and improve the reliability of wastewater services in the City of Greater Geraldton. 

This work includes the construction of a new wastewater pump station at the Southern end of Glenfield Beach Dr, as well as a new 2.2-kilometre wastewater pipeline, from the new wastewater pump station to the Glenfield Wastewater Treatment Plant, south of the development. 

Where is the work happening?

When is this happening?

Work is currently expected to be complete in mid 2024. 

How will this impact me?

Residents may notice noise, dust and increased vehicle activity in the area whilst we complete this work. 

We have a traffic management plan in place for sections of the dune system as we install the new pipeline. We ask that you please follow our signage, to help ensure the safety of our work crews as well as the Glenfield and visiting community. 

We appreciate construction work can be impactful, and we thank you for your patience and cooperation whilst this essential work is carried out. 

All areas impacted by our construction will be reinstated and is to be approved by the City of Greater Geraldton. 

 

Subscribe for project updates